Azizi Developments reports 79% completion on its Rêve project in Dubai's Riviera community. Key milestones include 100% structural build, 98% blockwork, 92% internal plastering, and 73% tiling. HVAC and MEP systems are 89% and 71% complete, while façade works are at 69% and external works at 63%. Swimming pool and elevator works are 57% and 48% complete, respectively, with overall finishes at 66%. Led by Gardinia Contracting, 1,100 workers are on-site, targeting a Q4 2026 completion. CEO Farhad Azizi emphasized the commitment to precision and design excellence throughout the project.